|

1988-89
| 1990 | 1991 | 1992
| 1993 | 1994 |
1995 | 1996 | 1997 | 1998
| 1999 | 2000
1988-89
- Horsetooth Reservoir's four dams (Horsetooth, Soldier Canyon,
Dixon and Spring Canyon) and dike (Satanka) are each raised from
3 to 8 feet in elevation, increasing the reservoir's ability to
store large flood flows, and addressing concerns that water in
the reservoir could potentially overtop one or more of the dams
during a major storm event.
1990
- October - Wet spot #1 develops on the downstream side of Horsetooth
Dam at an elevation of 5,355 feet above sea level.
1991
- Wet spot #2 develops above the left toe drain exit of Horsetooth
Dam at elevation 5,317.
- U.S. Bureau of Reclamation and Northern Colorado Water Conservancy
District staffs increase monitoring of seepage at Horsetooth Dam.
- First drill holes and piezometers installed downstream of left
dam abutment.
Back
1992
- June - The left toe drain at Horsetooth Dam begins to flow for
the first time.
- Additional drill holes and piezometers installed downstream
of left dam abutment.
Back
1993
- April - Reclamation's Safety Evaluation of Existing Dams (SEED)
inspection team completes inspections of Horsetooth Reservoir
and Soldier Canyon outlet works, and issues a favorable report.
The team consists of personnel from the State of Colorado, Reclamation,
and the District.
Reclamation and District personnel continue to monitor piezometer
readings and flow rates at Horsetooth Reservoir.
Back
1994
- Reclamation's SEED inspection team completes inspections
of toe drains and measuring stations at Horsetooth Reservoir,
and issues a favorable report.
Back
1995
- June 28, 1995 - Horsetooth Reservoir's surface water elevation
reaches a record high of 5,429.38 feet above sea level.
- Reclamation and District personnel continue to monitor piezometer
readings and flow rates at Horsetooth Reservoir.
Back
1996
- Wet spot #3 develops on the downstream side of Horsetooth Dam
at elevation 5,316.
- Piezometer readings and flow rates slowly increase between 1990
and 1996. These readings coincide with higher than average storage
levels at Horsetooth Reservoir.
Back
1997
- Wet spot #4 develops on the downstream side of Horsetooth Dam
at elevation 5,338.
Back
1998
- February -- The aerial extent of wet spot #4 expands significantly.
- June -- An independent technical consulting team completes a
full review of safety activities and releases its report to the
public.
- August -- Reclamation begins drilling test holes and installing
new monitoring equipment at all four of the reservoir's dams to
determine foundation conditions.
- August -- Reclamation releases its Comprehensive Facility Review
of Horsetooth Dam.
- August 31 -- First public meeting is held to update citizens
on current investigations and future plans at Horsetooth Reservoir.
- Reclamation and District personnel continue to monitor piezometer
readings and flow rates at Horsetooth Reservoir.
Back
1999
- January-March -- Test drilling at Horsetooth Reservoir's four
dams continues.
- Reclamation and District officials meet regularly to discuss
test results and plan future course of action.
- December 7-9 -- A consultant review board meets for a detailed
discussion of studies and to consider a plan of action for Horsetooth
Reservoir.
- December 10 -- A decision memorandum is signed authorizing
Reclamation to move forward with plans to modernize the dams at
Horsetooth Reservoir.
- December -- Reclamation publicly announces that modernization
of Horsetooth Reservoir's dams will likely begin in the fall of
2000.
Back
2000
- January 18, 24 -- Reclamation and District officials host public
meetings unveiling plans to modernize Horsetooth Reservoir's four
dams.
- April -- Reclamation officials begin seismic-refraction testing
to determine the depth of bedrock below Horsetooth's four dams.
- April -- District staff ask irrigators to assist in maintaining
water levels at Horsetooth Reservoir until late summer.
- March-April -- Horsetooth Reservoir water levels drop approximately
5 feet over seven weeks due to dry weather conditions and heavy
demand.
- May 3 -- Reclamation and the District announce they are hopeful
that remediation and modernization work on the dams at Horsetooth
Reservoir will begin in the fall of 2000. The $110-130 million
project awaits funding by Congress.
- Early June -- The draft Environmental Assessment is released.
It analyzes the alternatives to address the safety of Horsetooth
Reservoir's dams.
- July -- Continued hot, dry weather conditions make it difficult
to maintain water levels at Horsetooth Reservoir despite the cooperation
of irrigators utilizing local reservoir supplies.
- July 15 -- Reclamation and the District officials pledge to
maintain high water quality in the reservoir during construction
on the dams. Fort Collins officials voice concerns with the project
and water quality issues.
- August 3 -- Reclamation officials estimate the need for as many
as 50 trucks per day to transport rock, sand and gravel to Horsetooth
Dam during the construction project.
- August 4 -- The final Environmental Assessment is released.
- August 18 -- The last usable boat ramp at Horsetooth Reservoir
goes dry at elevation 5,359 due to falling water levels.
- October 3 -- Crews working at Horsetooth Reservoir find a sinkhole
near the left upstream toe of Horsetooth Dam.
- October 17-18 -- Reclamation and District crews begin working
around the clock to test the sinkhole near Horsetooth Dam. The
District and Reclamation conclude the sinkhole is the main source
of water seepage at Horsetooth Dam.
- October 23 -- Contractors begin filling the sinkhole near the
left toe of the dam with grout. District and Reclamation crews
then install a 100-square foot cap and thousands of cubic yards
of clay and rock.
- October 23 -- The District begins lowering the reservoir's surface
level, allowing Reclamation geologists and engineers to examine
anomalies at the bottom of the reservoir near Horsetooth Dam.
- October 24 -- Reclamation and the District announce water levels
at Horsetooth Reservoir will be drawn down to dead storage, below
elevation 5,295. At that point, the reservoir is essentially drained
except for pools of water behind the three east-facing dams -
Soldier Canyon, Dixon and Spring Canyon.
Back
|