|

Frequently-Asked
Questions About Horsetooth Reservoir Dams
1.
Are the dams at Horsetooth Reservoir safe?
All
the dams are safe, and are not about to fail. Continued frequent
and extensive monitoring indicates that all four dams are performing
safely. No unusual seepage has been detected through any of the
dams; foundation seepage is a concern only at Horsetooth Dam.
The modifications will ensure the continued safe operations of
the dams into the future. They provide defensive measures against
conditions that could arise in the future that would threaten
the large population living immediately below the dams. Reclamation
believes that these proactive measures are warranted to ensure
continued public trust and confidence in the facilities.
2.
If the dams are safe, whats being done to them?
Because
so many people live downstream from these dams, they must be brought
to the current state of the art of dam design and construction.
Three actions are being performed to modernize all four dams.
First, layers of sand and gravel are being added to each dam,
to allow normal seepage through the dams while preventing erosion
of the dams themselves ("piping").
Second, a berm of additional material is being added to the base
of each dam, to stabilize it in the case of an earthquake. Free iphone for you
Finally, an impervious blanket will be added at Horsetooth Dam
only. The blanket will cap about 4 _ acres with a plastic liner
covered with clay. It will prevent water from entering the exposed
limestone and seeping through the rock beneath the dam.
3.
What about the sinkholes that were discovered?
A
single seepage entry location (sometimes referred to as a sinkhole)
was revealed at Horsetooth Dam in late September 2000 as the water
level dropped. Its location was directly in line with the limestone
geology, confirming Reclamations predictions that the limestone
was a major culprit in allowing water to seep under Horsetooth
Dam. Sonar scans in 1999 had located this and other possible "anomalies."
For a few weeks in the fall of 2000, the pool at Horsetooth Dam
was drained to "dead storage" to treat the entry location
and to identify the other anomalies. The entry was plugged with
concrete and capped with plastic and clay before the reservoir
began rising again. Analysis of geologic samples and of data gathered
after sealing this entry allowed Reclamation to treat the foundation
seepage with an upstream blanket, rather than the concrete cutoff
wall originally planned. No other sinkholes were found near the
dam. The other anomalies were identified as erosion and deposits
left from original construction.
4.
Why does the water level have to be restricted during construction?
What impact will the restriction have on water supply, power, and
recreation?
During
a portion of the construction, the dams are temporarily less stable
than usual. Therefore, a lower water surface is required to reduce
the water pressure against the dams. After extensive investigation
and analysis by Reclamation, a water level restriction of 5360
feet was determined. This elevation reduces the water pressure
sufficiently, while still providing enough water in the reservoir
to serve needs. At 5360, Horsetooth will be approximately a third
full. Water levels will still fluctuate, but not rise above 5360
until construction is nearly complete.
During
construction, boating will be possible, but limited, from the
late spring into the summer. By working together, Larimer County
Parks and Open Lands and Reclamation extended the Swim Beach boat
ramp and constructed a new boat ramp specifically for low water
levels so boaters will still have water access.
5.
Whats the schedule for construction?
Phase
1 is construction of a filter, drain, and berm at Horsetooth Dam.
Construction on this phase began in March 2001, and is scheduled
to be complete in the summer of 2002. Phase 2 is construction
of filters, drains, and berms at each of the three east-facing
dams. It began in the October 2001 and is scheduled for completion
in the late summer of 2003. Reclamation plans to "relax"
the water level restriction during the last several months of
construction. Phase 3 will be construction of an upstream blanket
at Horsetooth Dam. Construction is planned for fall 2002. Closeout
activities will include landscape rehabilitation and road re-paving.
6.
How much will this work cost, and who pays for it?
The
estimated cost for the entire project is $105 million. That includes
the cost of exploration, design, and construction. Under the 1984
Safety of Dams Act, the Federal government pays 85% of the cost.
The remaining 15% is split among the project beneficiaries. In
this case, water users (the Northern Colorado Water Conservancy
District) pay 7.5% and power customers pay 7.5%
7.What
are the roles of the Bureau of Reclamation and the Northern Colorado
Water Conservancy District?
Horsetooth
Reservoir is a key part of the Colorado Big Thompson Project
(C-BT), built and owned by the Bureau of Reclamation. Consequently,
Reclamation is responsible for ensuring that the dams meet current
standards for public safety. The Northern Colorado Water Conservancy
District was formed to repay the costs of the C-BT Project. They
distribute water to irrigators and municipal and industrial water
users. The District also operates and maintains the Horsetooth
Reservoir dams, along with other C-BT facilities.
|